2004 Construction Awareness Program

 

Information Regarding O’Hare International Airport’s
Nighttime Construction and Maintenance Program for 2004


Only one construction project for he 2004 construction season will affect the Fly Quiet Program. Runway 9R-27L will be closed for sixty consecutive nights from early August to early October for a limited rehabilitation project. Consequently during this construction period, Runway 14R-32L will be closed for three consecutive nights due to the construction activities of the Runway 9R-27L project at the intersection of Runway 14R-32L. The phasing dates for the three consecutive nights of closure are pending.

For more information regarding the potential impacts relating to the preferential runway use under the Fly Quiet Program, please call Mr. Cyle Cantrell at 773-894-5490.

Fact: Runway 9R-27L is O’Hare’s second longest runway and one of the most utilized nighttime runways. Runway 14R-32L is O’Hare’s longest runway and also one of the most utilized for nighttime operations.
 

 

 